In order to make the pellet feed processing equipment run normally, prolong its service life and reduce failures, and improve economic efficiency, China Animal Husbandry Equipment Network made a few comments for reference.
1 Equipment installation and commissioning
1.1 Before installation, according to the equipment plan and foundation map, check whether the basic dimensions of each installation meet the requirements of the drawings. If there is any discrepancy, it should be repaired until the dimensions are correct before installation.
1.2 The installation personnel should be familiar with the installation requirements of each equipment and strictly follow the technical requirements for construction.
1.3 The equipment may cause deformation, damage or loss during transportation. Therefore, before installation, check and check the equipment list, and take corresponding measures to make the equipments in good condition and then install.
1.4 Before each equipment enters the installation site, it shall be numbered, and the installation process flow card and schedule shall be formulated. According to the requirements of the installation process sequence, the equipment shall be transferred to the site for installation.
1.5 Installation sequence: From top to bottom, install the connecting pipes and electrical equipment after the host equipment and the rack are in place.
1.6 Tools required for installation: Equipment and village materials must be available.
1.7 After the installation, the rotating parts of the equipment must be flexible and free of card, bump and impact sound. The connecting parts must be firm and sealed, and there must be no leakage, air leakage or oil leakage.
1.8 The installation of electrical equipment shall comply with the relevant provisions of the State. The direction of each line shall be clear, and there shall be no running or leakage of electricity. Wires and cables shall have protective casings to prevent rat bites.
1.9 After all the equipments have been installed, each single unit should be tested for empty vehicles, and the normal operation can be put into the load test.
1.10 Before the load test, the electronic batching scale and the packing scale are calibrated to achieve the specified accuracy.
1.11 Load operation for 8h, no problem can be handed over to the factory for production use.
2 Operation and use of
2.1 Before the driving, the equipment will be inspected by the staff on duty.
2.1.1 Whether there is any foreign matter falling into the equipment; whether the rotating parts are flexible, whether there is any card or collision phenomenon; whether the connecting parts are firm; whether there are leakage, gas leakage or oil leakage. If there is a fault, it should be eliminated in time.
2.1.2 Whether the gears have lubricating oil; whether the tension of the transmission belt is suitable; whether the hammer of the crusher, the die of the granulator and the pressure roller need to be replaced; whether the specifications of the sieve meet the requirements.
2.2 Control room personnel should master the daily production schedule and the storage of the main and auxiliary materials in order to dispatch production.
Aluminum Clip-in Commercial Ceiling Tile
Aluminum Clip-In Commercial Ceiling Tile,Commercial Ceiling Tiles,Galvanized Acoustic Ceiling Tiles,Galvanized Suspended Ceiling Tiles
Foshan Nanhai Lianxing Deli Decoration Materials Co.,Ltd , https://www.fstuodeli.com