Marble, granite stone wall wet construction plan

Marble and granite stone wall wet construction scheme: The craft standard is applicable to the decoration of indoor and outdoor walls, cylinders and door and window sets of marble, polished granite and prefabricated terrazzo for civil and public buildings.

Construction preparation:

2.1 Material requirements:

2.1.1 Cement: 325 ordinary Portland cement. There should be a factory certificate or a retest list. If it is more than three months after delivery, it should be used according to the test results.

2.1.2 White cement: 325 white cement.

2.1.3 Sand: coarse sand or medium sand, sieved before use.

2.1.4 Marble, polished granite, prefabricated terrazzo, etc.: Prepare according to the specifications and colors required by the design and drawings. However, the surface must not have defects such as hidden injuries and weathering. It should not be packed with fading materials.

2.1.5 Other materials: such as plaster, copper or galvanized lead wire, lead skin, hard plastic slats, matching pendants (galvanized or stainless steel connectors, etc.); should also be equipped with appropriate amount of marble or polished granite, Prefabricated terrazzo and other color gravel and mineral pigments; 107 glue and special plastic hose for filling the gap of the veneer.

2.2 Main equipment:

2.2.1 Scales, iron plates, half vats, small buckets, shovel, flat shovel, trolley, plastic hose, rubber bowl, watering can, alloy steel flat scorpion, alloy steel Drill Bit (φ5, for eye drilling), operating bracket, Bench drill, iron level ruler, square ruler, ruler plate, base ruler (3000~5000mm×40mm×10~15mm), support plate, line pendant, powder line package, high stool, wooden wedge, small table grinding wheel, cut Change marble grinding wheel, full Cutting Machine, open knife, gray board and lead (1mm thick), wooden trowel, iron trowel, fine wire brush, enamel, size hammer, small white wire, lead wire, cloth or cotton Silk, tiger pliers, spatula, box ruler, nails, red pencils, brushes, Tool bags, etc.

2.3 Working conditions:

2.3.1 Handle the structure acceptance. A small number of types of work (hydropower, ventilation, equipment installation, etc.) should be done in front, and ready to process the water, power supply, etc. required for the veneer.

2.3.2 The inner wall surface is good for 50cm horizontal line (the outdoor wall surface is good for ±0 and the horizontal level control line for each layer).

2.3.3 Scaffolding baskets should be supported in advance. Double-row racks should be used (the outdoor high-rises should adopt hanging baskets, multi-layer can use bridge shelves, etc.), and the horizontal and vertical rods and tie rods should be separated from the door window angle by 150-200mm. The shelf height must meet the construction requirements.

2.3.4 Door and window frames must be properly positioned (right, vertical, and secure, and have sufficient margin for the size of the marble). At the same time, the gap should be blocked with 1:3 cement mortar. The caulking materials used for the seams of aluminum alloy door and window frames shall meet the design requirements, and the plugs shall be tightly packed and the protective film shall be pasted.

2.3.5 Marble, polished granite or prefabricated terrazzo should be stacked indoors, under the square, check the quantity and specifications, and pre-lay, flower, number, etc., in order to prepare for the official paving Take it.

2.3.6 Large-scale construction should be released before construction and sample preparation. After passing the appraisal by the quality inspection department, it must be jointly identified by the design, Party A and the construction unit. The team can organize the construction according to the requirements of the model.

2.3.7 The stone materials entering the site shall be checked and accepted. When the color is uneven, it shall be selected and tested if necessary.

Operating process:

3.1 Process:

3.1.1 Book type small size block (side length less than 40mm) process:

Base treatment→hanging vertical, sleeve, finding rules, plastering cake→wiping mortar→elastic analysis→blocking material→dip block→inserted block→surface joint and seam

3.1.2 Large-size bulk material (side length greater than 40mm) Process:

Construction preparation (drilling, grooving → wearing copper wire or galvanized wire and block fixing → tying, fixing steel mesh → hanging vertical, looking for elastic wire → installing marble, polished granite or precast terrazzo → layered grouting →Blank marble, granite stone wall wet construction plan

The craft standard is applicable to the decoration of interior and exterior walls, cylinders and door and window sets of marble, polished granite and prefabricated terrazzo for civil and public buildings.

Cable Tie

Cable tie is used to tie things together. According to the material, it can be divided into nylon cable ties, stainless steel cable ties, plastic-sprayed stainless steel cable ties, etc.; according to the function, it can also be divided into ordinary cable ties, retractable cable ties, label cable ties, heavy tension cable tie, etc. The cable tie is made of UL-approved nylon 66 material with a fire rating of 94V-2. It has the characteristics of acid resistance, corrosion resistance, good insulation, resistance to aging, light weight, safety, non-toxicity, and strong durability. Operating temperature is minus 40 to 90 degrees.

B182_1B203_1B189_1

Cable Tie,Nylon Cable Tie,Plastic Cable Tie,Pound Zip Cable Ties

Behappy Crafts (suzhou)Co.,Ltd , https://www.craftsbehappy.com

This entry was posted in on